Augusta University theater to close for estimated $1.5 million renovation

Category:

• Published:

Exterior of Augusta University's Grover C. Maxwell Performing Arts Theatre.

Augusta University’s 58-year-old Grover C. Maxwell Performing Arts Theatre is scheduled to close Dec. 7 for an approximately five-month renovation, pausing the university performances and community events regularly held there.

The project has an estimated price tag of $1.5 million. Crews expect to finish by the end of March, and audiences are expected to return in April 2027.

Renovations will replace every seat, with new seats designed for comfort, and overhaul the theatre’s technology. Plans also call for new restrooms in the lobby and backstage areas. The current sound system is to be moved to a dedicated booth inside the theatre.

Jeffrey Keenan, Augusta University’s assistant vice president for student affairs facilities, said the theatre has served the university and community as a gathering place for nearly six decades. He said the work is intended to modernize the facility and improve the audience experience, with students, campus partners and community guests expected to benefit when it reopens.

The university said theatre staff have worked with campus and community partners to find alternative locations for events during construction. Those events are expected to move to other venues in the CSRA, though the specific locations were still being determined.