Update: Augusta Panel Recommends Denial of Data Center Rezoning

Category:

,

• Published:

File photo: John H. Ruffin Jr. Courthouse, Augusta-Richmond County Judicial Center. Photo: Augusta-Richmond County official website.File photo: John H. Ruffin Jr. Courthouse, Augusta-Richmond County Judicial Center. Photo: Augusta-Richmond County official website.

The Augusta Planning Commission voted 6-4 Monday to recommend denying the rezoning needed for the proposed Nixon Technology Campus near Mike Padgett Highway. The recommendation does not take the project off the table: the Augusta Commission is expected to consider the rezoning Tuesday, Dec. 1, and will have the final say.

Developers said the campus could include as many as seven buildings, with at least 500 feet between the data-center buildings and nearby homes. The facility has no confirmed end user. Developers estimated that, when fully developed, it could bring Richmond County approximately $38 million in annual gross revenue and around 1,000 permanent jobs.

Electricity costs and the development’s long-term effect on nearby neighborhoods were among the issues raised. A community member asked what would stop added data-center costs from being passed to customers after the current rate freeze ends in 2028. Developers pointed to Georgia Public Service Commission regulations they said are intended to protect customers from those costs.

Richmond County resident Zakiya Mabery said the developer compared data-center development with building the interstate highway system. She cited displacement, divided neighborhoods and effects lasting generations as part of that history. Other speakers also questioned the lasting effects of industrial development near established neighborhoods.

Augusta Director of Planning Daisha Burke outlined the recommended development pattern and stressed separating residential and industrial uses. Two planning commissioners supported approving the rezoning, while another argued for postponing the decision by 60 days. Community members had an opportunity to speak directly to commissioners. Developers presented their plans after multiple changes to the meeting date and time.

Victoria Sterling
News Now Georgia

Share This Story

Make a one-time donation

Thanks for your generosity!