College Park Botanical Garden’s First Phase Is More Than Half Complete

Category:

• Published:

AI-generated illustration: News Now Georgia topic graphic. Illustration credit: News Now Georgia.

More than half of phase one is complete at College Park’s planned Roderick Gay Botanical Garden, a 40-acre project expected to cost $13 million and open in 2027. The garden is being built on the former Camp Truitt/4-H site off Herschel Road.

Councilman Roderick Gay toured the construction site and estimated the work would be finished in about three months, though he did not give a specific completion date. The site looks noticeably different from its October 2025 groundbreaking. Crews are repurposing structures and materials, and Gay said the six remaining cabins will be conserved under a conservancy decision that will govern the garden.

Construction has encountered an underground utility issue. Senior project manager Philip Brown said some utilities were missing from the drawings, requiring updated as-built records. A gas-line reroute was considered, and planners meet weekly to track progress and scheduling. Officials said construction was otherwise going successfully. Worker Jason Benson said the project was making substantial progress.

Plans include a facility where families can sit and learn about the site’s story, as well as galas and fundraising events. Gay said crews removed 100 loads of dirt to create waterfalls 15 feet wide. The garden is also planned to have floating fountains for weddings and a dancing fountain, with families able to walk around the water feature.

Brown said the garden is intended to help young people learn about Camp Truitt’s history, native plants, gardening and community collaboration. Trees marked with silver tags are to be kept; Gay said all the trees have been cataloged and his wife helped ensure as many as possible would be saved. The black oak is the garden’s symbol.

Marcus Jones
News Now Georgia